UK energy network operators abolish 10GW of ‘zombie’ connection projects
Image courtesy ENA
Electricity network operators in the UK have abolished 10GW of so-called ‘zombie’ projects since December 2023, finds the Energy Networks Association (ENA).
According to ENA in a release, the achievement has been possible thanks to work being undertaken by network operators, the regulator and the system operator through ENA’s Strategic Connections Group, which was launched less than a year ago in December.
The initiatives have seen stalled or speculative schemes – that were characterised by the regulator last year as zombie projects – removed from the grid connections queue.
Over the coming months, the Group is working on further initiatives as part of the next phase of the process, including ensuring a more effective and cohesive connection process between the transmission and distribution networks.
ENA and their network operator members are working with the regulator to assess what would be needed to deliver this coordination, including in terms of codes or new licence changes to facilitate it.
Have you read:
UK Networks Association sets out industry action plan for grid capacity
British MPs warn of continued lags in grid connections queue
Commenting in a release was Lawrence Slade, chief executive of Energy Networks Association: “Removing these stalled schemes is a necessary step to make the UK’s grid connection process faster but it’s just one part of the solution and work must continue at pace. We’re taking measures to more closely coordinate the connections process between distribution and transmission networks and we’re working with the government and regulator to help ensure the planning system is ready to enable the connections needed for the UK’s clean energy future.
“We also shouldn’t forget that these projects are a sign that the ‘connection queue’ itself requires further reform, as there was 252GW more generation and supply capacity in the queue last year than is required by 2050 in even the most ambitious plans for the UK’s grid.”
ENA’s Strategic Connections Group, made up of network operators and industry partners, was launched last year to accelerate the speed of grid connections.
It has prioritised practical reforms and is advocating for strategic changes to the UK’s planning processes that are necessary to make grid connections even faster.
Actions being taken include:
- Ensuring all projects within the queue are ‘on track’ and meeting the milestones set out within their contracts.
- Where a project is behind schedule and hasn’t reached the milestone it should have, network companies are liaising with the developer and discussing the reason behind the delay, as well as assisting with progression of the project to meet any current and future milestones.
- Where a project has completely stalled and is no longer progressing, networks are removing these from the queue and terminating connection contracts.
ENA adds that electricity transmission and distribution networks connected more projects last year than any previous year, with 9.7GW connected over the 12 months from April 2023.