Peel Land has submitted revised Haydock Point plans for approval. The 1.3 million sq ft manufacturing and logistics campus includes new highway infrastructure, HGV provision and employment space forecast to support 1,845 jobs.


Peel Land has submitted an outline planning application for a 1.3 million sq ft manufacturing and logistics campus at Haydock Point in St Helens, advancing the scheme from public consultation into the formal planning process.

The proposed development covers more than 100 acres close to Junction 23 of the M6 and is forecast by Peel to support 1,845 jobs and more than £110 million in annual gross value added. The indicative masterplan includes two large units on the northern part of the site, smaller employment buildings further south and dedicated HGV provision.

Unlike the consultation launched in August, the submission gives St Helens Council and statutory consultees a defined application against which highways, ecology, drainage, design and other technical evidence can be assessed. An outline consent would establish the main development parameters rather than approve the detailed design of every building.

Transport infrastructure remains one of the largest engineering elements in the proposal. Peel plans about one kilometre of new road to redirect traffic approaching Haydock Point before the motorway junction, while the wider scheme includes changes to the northern arm of the A49 and connections towards the A580 East Lancashire Road.

A campus containing manufacturing and logistics occupiers would generate several traffic patterns simultaneously. Employee movements concentrate around shift changes, freight vehicles can arrive throughout the day and construction traffic is substantial while plots and shared infrastructure are being built, requiring the highway design to accommodate different peaks without transferring congestion from the site entrance to surrounding roads.

HGV infrastructure is also unusually prominent in the masterplan. Earlier consultation material included secure parking, driver welfare facilities and an alternative fuel hub, allowing the site to support heavy vehicles as well as the industrial buildings they serve.

Dedicated HGV space can reduce informal parking and queuing around surrounding roads, but it also requires additional hardstanding, drainage, vehicle circulation and separation from employee and pedestrian routes. Electric charging or other alternative fuel infrastructure would add further utility and safety requirements depending on the final configuration.

Peel has reduced the proposed floorspace by around 500,000 sq ft compared with the 1.8 million sq ft scheme advanced in 2017. That earlier proposal was ultimately refused following appeal in 2021, while the planning policy position subsequently changed when the site was removed from the Green Belt and safeguarded for future employment development in the St Helens Borough Local Plan adopted in 2022.

The revised application consequently enters the planning system under a different land allocation, although that does not remove the need to demonstrate acceptable effects on transport, landscape, ecology and local infrastructure. Outline planning establishes where and at what scale development may proceed, with detailed building design generally following through later reserved matters applications if permission is granted.

Landscaped and wildlife areas, new trees and walking and cycling routes were also incorporated into the consultation scheme. Those uses compete for the same site area required by industrial plots, roads, drainage and service infrastructure, so environmental provision has to be integrated into the engineering layout rather than added after the developable land has been fixed.

Surface water management becomes particularly important across a campus of this scale because roofs, yards and roads create extensive impermeable areas. Run-off has to be collected and attenuated before controlled discharge, while areas used by heavy vehicles may also require measures to contain pollutants carried from road surfaces.

Utilities will present another constraint once individual occupiers are identified. Manufacturing buildings can have substantially different electricity, gas, water and data requirements from conventional distribution sheds, and HGV charging or other alternative fuel infrastructure could increase electrical demand further.

An outline consent determines where development can occur but does not guarantee that every plot can immediately obtain the power capacity a future occupier requires. Electricity reinforcement, water connections and other shared services may therefore influence the order in which buildings are brought forward.

Peel is presenting Haydock Point as a regional employment and investment scheme as well as a property development. Managing director Stephen Wild said the application would be accompanied by a social value strategy including £20 million of local construction spend, while the economic assessment forecasts substantial operational GVA once the campus is occupied.

Those benefits will depend on plots being serviced and filled rather than simply receiving planning permission. A 1.3 million sq ft development is likely to be delivered in phases, with roads, drainage, utilities and other shared infrastructure required before or alongside individual buildings.

That phasing exposes the developer to capital expenditure ahead of full occupier income and makes shared infrastructure a commercial consideration as well as a planning requirement. If power, roads or drainage are delivered too slowly, otherwise marketable plots can remain unusable; if too much infrastructure is built ahead of demand, capital remains tied up before rental income arrives.

The planning application now allows those assumptions to be tested against detailed evidence rather than concept material. Haydock Point has already moved through several years of planning revisions and policy change, so the next substantive milestone is whether the submitted access, infrastructure and development parameters can secure outline consent.


Stories for you


  • Magnera commissions five layer blown film line

    Magnera commissions five layer blown film line

    Magnera has commissioned a new blown film line in Germany. The Dombühl investment adds five layer production capability for lightweight and elastic films used in personal care and healthcare applications.


  • RobCo passes bn as autonomous robotics expands

    RobCo passes $1bn as autonomous robotics expands

    RobCo has passed a $1 billion valuation in industrial robotics. The Munich company is preparing its first autonomous bimanual system while expanding manufacturing, assembly and customer deployments across the United States.