Energy and powerNews

Dutch cabling contract signed to expedite project lead times

Dutch cabling contract signed to expedite project lead times

Image courtesy Alliander

In a bid to speed up the delivery and completion of critical power grid projects, Alliander, parent company of Dutch utility Liander, has signed a framework agreement with Twentsche Kabelfabriek (TKF) to ensure a steady supply of 50kV cables for Liander projects.

For the next few years, the agreement should reduce delivery lead times, facilitating the start of projects aimed at advancing the energy transition.

Due to prolonged project lead times stemming from materials shortage, Liander and Alliander-owned tech and intelligent energy infrastructures developer Qirion jointly submitted a proposal for 50kV cable systems.

The agreement pertains to the supply and installation of materials for 50kV cable systems, with an emphasis on environmentally sustainable production, which is included as a selection criterion in the specifications.

The contract was awarded to TKF, which will be responsible for ensuring a sufficient supply of 50kV cables for Liander’s projects, starting 2023.

Have you read:
Swissgrid partners with RTEi on AC cable feasibility studies
Google and UK Power Networks chart AI-driven electric cable maps
Soaring electricity demand must be ‘good citizen of the grid’ says California energy chief

The framework agreement streamlines coordination with TKF, reducing lead times for deliveries, simplifying project planning and thereby enabling quicker project initiation.

Stressed-out grid and delayed projects

According to Alliander, the evolving dynamics of energy supply and demand are placing significant stress on the Netherlands’ electrical grid.

The country will see approximately one in three streets undergo excavation in the forthcoming years to prepare the power network for oncoming supply.

The challenge, however, lies in executing all the necessary work punctually and in line with quality standards.

Additionally, grid expansion could lead to a shortage of materials, resulting in prolonged project lead times and the question of securing an adequate supply of cables.

The first delivery of 50kV cables under the new framework agreement between Alliander and TKF has already been successfully completed.

On September 20, the first cables were rigorously tested and put into operation on a Liander project, carried out by Qirion, which leverages the new partnership with TKF.