Studsvik and ReNu plan Fukushima waste pilot

Studsvik and ReNu plan Fukushima waste pilot

Studsvik and ReNu will adapt radioactive waste treatment for Fukushima. Their agreement covers technical advice and a proposed inDRUM pilot design suited to Japanese seismic and regulatory requirements; construction, permissions and commissioning remain unconfirmed.


Studsvik and Japanese nuclear engineering company ReNu Industries have agreed technical advisory work on adapting inDRUM radioactive waste treatment for a proposed pilot plant in Fukushima Prefecture. The Swedish company’s technology uses thermal processing inside containers to treat problematic waste streams. The arrangement begins engineering work on a Japanese configuration; it is neither a construction contract nor an operating authorisation.

Studsvik’s Japanese subsidiary and ReNu signed the agreement in Nyköping on 21 October, with the arrangement announced on 23 October. Studsvik will provide design information and technical advice, while ReNu takes responsibility for developing the proposed pilot configuration. The design must account for local seismic requirements, Japan’s nuclear regulatory framework and the composition of the waste that might be accepted for treatment.

Before any plant could be built, the partners would need to define a waste inventory, assess the engineering design and follow applicable Japanese approval procedures. No confirmed site construction timetable, treatment throughput, capital budget or operating licence has been disclosed. ReNu’s immediate task is to determine how the thermal process and supporting systems could meet the conditions of a pilot project.

inDRUM is a batch thermochemical process that treats waste within a container. Heating is used to remove free liquids, break down organics and reduce certain corrosive or chemically reactive characteristics, potentially allowing problematic material to proceed to the next stage of waste management. Radioactive constituents do not disappear during treatment. Residues and any secondary waste still require characterisation, containment and appropriate routes for storage or disposal.

The technology is intended for difficult waste streams, including some transuranic material and waste across different activity categories. Treatment suitability is controlled by the individual waste package: its moisture, organic content, chemical reactivity, radioactivity and compatibility with the vessel and process. Those parameters need to be established before assuming a package can be heated safely or that the output will meet a particular disposal acceptance criterion.

Designing a pilot involves defining a permitted feed envelope and the controls around the heating process. Waste characterisation affects the treatment temperature and duration, the handling of gases and vapours, and the required containment and monitoring equipment. The partners have not disclosed Japanese pilot process settings or a measured reduction factor; the engineering work is intended to develop a configuration against which such performance can eventually be tested.

Seismic qualification introduces further requirements for building structures, supports, connected services and safety functions. Equipment and containment arrangements must continue to perform as required under the site-specific design basis, while the operator must demonstrate compliance with national radioactive material handling rules. It is not yet known which physical changes to Studsvik’s standard equipment would be required for that Japanese application.

Waste treatment at Fukushima is technically demanding because streams can differ markedly in their origin, contamination and physical form. A process that reduces liquid content or destroys organics may help convert certain wastes into a more stable state for subsequent management, but it does not settle the question of final disposal. Any claims about volume reduction, exposure savings or operating costs would depend on the selected waste inventory and measured pilot results, which have not been provided for this Japanese proposal.

Studsvik intends to operate its own inDRUM facilities in Sweden but enter other markets by licensing the technology and working with local companies. Under this approach, ReNu would develop and potentially operate a Japanese treatment plant subject to the relevant authorisations, while Studsvik provides technology and support. The choice of local delivery partner does not transfer responsibility for Japanese regulatory compliance back to the Swedish technology supplier.

A nuclear waste facility’s safety case is tied to its site, operator, permitted inventory and equipment. Data from a process proven elsewhere may support an assessment, but do not alone establish that a different feed material can be processed under Japanese conditions. ReNu will need to establish the required design evidence and seek any relevant permissions before progressing from a proposal to physical works.

The Fukushima work is separate from Studsvik’s earlier Norwegian spent fuel management framework. Both involve radioactive material, but their scopes, counterparties and proposed operations differ. The present arrangement targets the technical design of a Japanese application of in-container thermal treatment, rather than transportation or storage of spent fuel under a long-term service framework.

The immediate milestone is a technically defined pilot project with its own waste envelope, facility layout and approval pathway. Without those details, the agreement cannot establish the cost, scale or schedule of a Fukushima plant. It confirms a route for adapting an existing treatment technology to Japanese conditions, with commercial deployment dependent on subsequent engineering and regulatory decisions.


Stories for you


  • WITT details industrial gas mixing and protection controls

    WITT details industrial gas mixing and protection controls

    WITT outlines integrated gas mixing, pressure regulation and safety controls. Its FABTECH presentation covered existing MEM+ mixers and protective valves, with equipment selection dependent on gas compatibility, operating pressure and withdrawal rate.


  • Chukotka icebreaker reaches first reactor power milestone

    Chukotka icebreaker reaches first reactor power milestone

    Chukotka reaches first nuclear reactor start-up milestone at Baltic Shipyard. The starboard RITM-200 unit achieved minimum controlled power on 19 October; the second reactor and full shipboard plant still need further tests.