EDF and Terna launch three-point power refurbishment project
Image courtesy 123rf
EDF and Terna, transmission system operators (TSOs) in France and Italy respectively, are working together on a power refurbishment project between Corsica, Sardinia and Tuscany.
The two transmission operators are collaborating to refurbish the SACOI2 power line in a project known as SACOI3, which will increase and secure the power supply system between the three territories.
Listed in 2015 in Corsica’s Pluriannual Energy Program and recognised by the European Union as a Project of Common Interest in 2017, the SACOI3 project meets French and Italian energy policy challenges.
The project makes it possible to double Corsica’s import capacity to 100MW and to support the strong development of renewable energies. Co-financing for the project was approved by the Italian and French regulators in January 2024.
Have you read:
Italy’s Terna announces €16.5bn investment plan guided by twin transition
EDF launches UK’s first heat pump tariff
Preliminary works will start in the second quarter of 2024.
The project will take five years to complete and includes the construction of three new converter stations, two new power lines (underground and submarine) and reinforcement work on the existing overhead power line between Lucciana and Bonifacio.
The tender for the construction of three converter stations in Sardinia, Corsica and Tuscany was won by the Hitachi Energy, Razel bec and Pelligrini consortium.
Commenting in a release, Antoine Jourdain, director of EDF SEI, said: “EDF is proud to be working alongside Terna to strengthen the quality of power supply to Corsica, Sardinia and Tuscany.
“The SACOI3 project fully illustrates our objective of strengthening the power grid in non-interconnected areas to guarantee continuity and quality of supply for customers and fully support the energy transition ambitions of our territories”.